Location/Size: Elmore County, Idaho. Project consists of 60 wind turbines with generating capacity of 138 megawatts (MW).
Eagle Take Permit Issued/Expires: 7/9/2024 - 1/31/2044
Authorized Take: 28 Golden Eagles and 1 Bald Eagle over 20 years
Compensatory Mitigation Required: Eagle take must be offset at a 1.2:1 ratio using a Service-approved method.