FINAL ADDENDUM TO ECONOMIC ANALYSIS OF CRITICAL HABITAT DESIGNATION FOR THE CAROLINA HEELSPLITTER
May 2002
PREFACE
The U.S. Fish and Wildlife Service has added this preface to all economic
analyses of critical habitat designations:
"The standard best practice in economic analysis is applying an approach that measures costs, benefits, and other impacts arising from a regulatory action against a baseline scenario of the world without the regulation. Guidelines on economic analysis, developed in accordance with the recommendations set forth in Executive Order 12866 ("Regulatory Planning and Review"), for both the Office of Management and Budget and the Department of the Interior, note the appropriateness of the approach:
'The
baseline is the state of the world that would exist without the proposed action.
All costs and benefits that are included in the analysis should be incremental
with respect to this baseline.'
"When
viewed in this way the economic impacts of critical habitat designation involve
evaluating the 'without critical habitat' baseline versus the 'with critical
habitat' scenario. Impacts of a designation equal the difference, or the increment,
between these two scenarios. Measured differences between the baseline and
the scenario in which critical habitat is designated may include (but are
not limited to) changes in land use, environmental quality, property values,
or time and effort expended on consultations and other activities by federal
landowners, federal action agencies, and in some instances, State and local
governments and/or private third parties. Incremental changes may be either
positive (benefits) or negative (costs).
"In
New Mexico Cattle Growers Ass'n v. U.S.F.W.S., 248 F.3d 1277 (10th
Cir. 2001), however, the 10th Circuit recently held that the baseline approach
to economic analysis of critical habitat designations that was used by the
Service for the southwestern willow flycatcher designation was 'not in accord
with the language or intent of the ESA.' In particular, the court was concerned
that the Service had failed to analyze any economic impact that would result
from the designation, because it took the position in the economic analysis
that there was no economic impact from critical habitat that was incremental
to, rather than merely co-extensive with, the economic impact of listing the
species. The Service had therefore assigned all of the possible impacts of
designation to the listing of the species, without acknowledging any uncertainty
in this conclusion or considering such potential impacts as transaction costs,
reinitiations, or indirect costs. The court rejected the baseline approach
incorporated in that designation, concluding that, by obviating the need to
perform any analysis of economic impacts, such an approach rendered the economic
analysis requirement meaningless: 'The statutory language is plain in requiring
some kind of consideration of economic impact in the CHD phase.'
"In
this analysis, the Service addresses the 10th Circuit's concern that we give
meaning to the ESA's requirement of considering the economic impacts of designation
by acknowledging the uncertainty of assigning certain post-designation economic
impacts (particularly section 7 consultations) as having resulted from either
the listing or the designation. The Service believes that for many species
the designation of critical habitat has a relatively small economic impact,
particularly in areas where consultations have been ongoing with respect to
the species. This is because the majority of the consultations and associated
project modifications, if any, already consider habitat impacts and as a result,
the process is not likely to change due to the designation of critical habitat.
Nevertheless, we recognize that the nationwide history of consultations on
critical habitat is not broad, and, in any particular case, there may be considerable
uncertainty whether an impact is due to the critical habitat designation or
the listing alone. We also understand that the public wants to know more about
the kinds of costs consultations impose and frequently believe that designation
could require additional project modifications.
"Therefore,
this analysis incorporates two baselines. One addresses the impacts of critical
habitat designation that may be 'attributable co-extensively' to the listing
of the species. Because of the potential uncertainty about the benefits and
economic costs resulting from critical habitat designations, we believe it
is reasonable to estimate the upper bounds of the cost of project modifications
based on the benefits and economic costs of project modifications that would
be required due to consultation under the jeopardy standard. It is important
to note that the inclusion of impacts attributable co-extensively to the listing
does not convert the economic analysis into a tool to be considered in the
context of a listing decision. As the court reaffirmed in the southwestern
willow flycatcher decision, 'the ESA clearly bars economic considerations
from having a seat at the table when the listing determination is being made.'
"The
other baseline, the lower boundary baseline, will be a more traditional rulemaking
baseline. It will attempt to provide the Service's best analysis of which
of the effects of future consultations actually result from the regulatory
action under review - i.e. the critical habitat designation. These costs will
in most cases be the costs of additional consultations, reinitiated consultations,
and additional project modifications that would not have been required under
the jeopardy standard alone as well as costs resulting from uncertainty and
perceptional impacts on markets."
DATED: March 20, 2002
INTRODUCTION
In July 2001, the
U.S. Fish and Wildlife Service (the Service) proposed designation of critical
habitat under the Endangered Species Act of 1973, as amended (the Act) for
the Carolina heelsplitter (Lasmigona decorata) on portions of the Lynches
River and nine creeks in North Carolina and/or South Carolina. Because the
Act also calls for an economic analysis of the critical habitat designation,
the Service released a Draft Economic Analysis of Critical Habitat Designation
for the Carolina Heelsplitter (hereafter DEA) for public review
and comment in March 2002.
This addendum to the
DEA addresses issues raised in the public comments to the DEA.
As such, the Addendum considers newly available information and revisits the
assumptions and analytic conclusions presented in the DEA in light
of the new information. . After considering the public comments on the proposed
rule, the Service made no revisions to the critical habitat designation for
the Kootenai River population of the White Sturgeon (hereafter "sturgeon").
This Addendum, therefore, primarily addresses the inclusion of estimatedbaseline
impacts associated with the listing of the sturgeon. Public comments specific
to the DEAare also considered and addressed in this Addendum.
In summary, the impacts included in this Addendum include:
REVISIONS
TO THE DRAFT ECONOMIC ANALYSIS
The following sections describe the implications of, and responses to, public comments to the DEA, as well as additional research on the analysis presented in the DEA. A number of the revisions affect the magnitude of the expected costs of this designation. The revised estimates result from evaluation of the information provided by the public during the comment period and additional research conducted pursuant to these public comments. Furthermore, section 4 of the DEA has been modified to update the consultation, technical assistance, and project modification costs and presents the expected costs of this designation by proposed critical habitat unit. Section numbers presented in the headers of this Addendum refer to the section numbers of the DEA.
SECTION
3: IMPACTS OF SECTION 7
The following section presents an expanded discussion of the types and (where data is available) likely magnitude of impacts associated with both the listing of the heelsplitter and subsequent designation of critical habitat for the species. The time period over which impacts are estimated is 10 years.
3.1 Impacts of Section 7 Implementation on Activities Affecting Critical Habitat Units in North Carolina
3.1.2 Road and Bridge Construction
The North Carolina Department
of Transportation (NCDOT) commented that many NCDOT projects requiring section
7 consultations for aquatic species have involved bridge replacement projects.
NCDOT also emphasized the difficulty of estimating the number of projects
that will require formal consultation, but noted that the department actively
works to avoid the need for formal consultation. Based on new information
provided by NCDOT, this analysis estimates that two formal consultations
in Unit 1 and one consultation in Unit 2 will occur over the next ten years.
NCDOT also commented that critical habitat for the heelsplitter had not been designated during the construction of the East Charlotte Outer Loop in Mecklenburg County, North Carolina. Therefore, the word "critical" has been deleted from paragraph 46 of the DEA.
Section
3.2 Impacts
of Section 7 Implementation on Activities Affecting Critical Habitat Units
in South Carolina
3.2.2 Road and Bridge Construction
3.2.3 Residential Development
Pursuant to the Section 4 of the Endangered Species Act, which requires the Service to consider economic impacts associated with each proposed critical habitat unit, predicted future consultations are now presented by unit. Based on the past consultation history, this analyis predicts five informal consultations in Unit 6 over the next ten years.
3.3 Summary
of Impacts
|
Exhibit
3-1 UPPER-BOUND
ESTIMATE OF THE TOTAL NUMBER OF ACTIVITIES |
|||||
|
Landowner or Manager |
Current or Future Activities |
Federal Nexus |
Technical Assistance |
Future Consultations |
|
|
Informal |
Formal |
||||
|
Private Landowners |
Residential Development |
ACOE section 404 permit |
70 |
75 |
5 |
|
Road/Bridge Construction |
US DOT funding |
50 |
25 |
3 |
|
|
Interbasin transfer of water |
FERC |
n/a |
0 |
1 |
|
|
Beaver damage management |
USDA |
n/a |
1 |
0 |
|
|
Flood Response |
FEMA |
n/a |
2 |
0 |
|
|
EPA Water Quality Standards |
EPA oversight |
10 |
10 |
0 |
|
|
Total |
130 |
113 |
9 |
||
|
Exhibit
3-2 UPPER-BOUND
ESTIMATE OF THE TOTAL NUMBER OF ACTIVITIES |
|||||
|
Landowner or Manager |
Current or Future Activities |
Federal Nexus |
Technical Assistance |
Future Consultations |
|
|
Informal |
Formal |
||||
|
Private Landowners |
Residential Development |
ACOE section 404 permit |
25 |
5 |
0 |
|
Road/Bridge Construction |
US DOT funding |
45 |
3 |
0 |
|
|
Forestry |
US Forest Service |
n/a |
170 |
0 |
|
|
EPA Water Quality Standards |
EPA oversight |
n/a |
10 |
0 |
|
|
Total |
70 |
188 |
0 |
||
|
Exhibit
3-3 UPPER-BOUND
ESTIMATE OF THE TOTAL NUMBER OF ACTIVITIES |
|||
|
Unit |
Current or Future Activities |
Informal Consultations |
Formal Consultationsa |
|
1 |
Residential Development |
50 |
3 |
|
Road/Bridge Construction |
15 |
2 |
|
|
EPA Water Quality Standards |
5 |
0 |
|
|
Interbasin Transfer of Water |
0 |
1 |
|
|
2 |
Residential Development |
25 |
2 |
|
Road/Bridge Construction |
10 |
1 |
|
|
Beaver Damage Management |
1 |
0 |
|
|
Flood Response |
2 |
0 |
|
|
EPA Water Quality Standards |
5 |
0 |
|
|
3 |
Road/Bridge Construction |
1 |
0 |
|
EPA Water Quality Standards |
2 |
0 |
|
|
4 |
Road/Bridge Construction |
2 |
0 |
|
EPA Water Quality Standards |
2 |
0 |
|
|
5 |
Forestry |
100 |
0 |
|
EPA Water Quality Standards |
3 |
0 |
|
|
6 |
Residential Development |
5 |
0 |
|
Forestry |
70 |
0 |
|
|
EPA Water Quality Standards |
3 |
0 |
|
|
Subtotal of Informal and Formal Consultations |
301 |
9 |
|
|
Technical Assistanceb |
200 |
||
|
Total |
510 |
||
|
a
This analysis assumes that all of the consultations will involve costs
to the Service, an Action agency, and a third party. |
|||
ESTIMATE OF COSTS OF DESIGNATING CRITICAL HABITAT FOR THE HEELSPLITTER
This section presents an analysis of the section 7 costs associated with the heelsplitter and its proposed critical habitat, by unit. This analysis parallels that presented in Section 4 of the DEA. The consultation, project modification, and total cost tables presented in Section 4 of the DEA have been modified to reflect updates to the cost model.
4.2 Estimated
Costs of Consultations and Technical Assistance
Estimates of the cost of an individual consultation reported in the DEA (Table 4-1) were developed from a review and analysis of historical section 7 files from a number of Service field offices around the country. The cost model developed from these files was recently updated. Therefore, the costs reported in Section 4 of the DEA have been modified to reflect this updated model.
Per-effort costs associated
with formal consultations, informal consultations, and technical assistance
calls are presented in Exhibit 4-1. The low and the high scenarios represent
a reasonable range of costs for each type of interaction. For example, when
the Service participates in technical assistance with a third party regarding
a particular activity, the cost of the Service’s effort is expected
to be approximately $260 to $680. The cost of the third party’s effort
is expected to be approximately $600 to $1,500.
|
Exhibit
4-1 ESTIMATED
ADMINISTRATIVE COSTS OF CONSULTATION AND |
||||||
|
Critical Habitat Impact |
Scenario |
Service |
Action |
Third Party |
Biological |
Total Cost |
|
Technical Assistance Effort |
Low |
$260 |
$0 |
$600 |
$0 |
$860 |
|
High |
$680 |
$0 |
$1,500 |
$0 |
$2,180 |
|
|
Informal Consultation |
Low |
$1,000 |
$1,300 |
$1,200 |
$0 |
$3,500 |
|
High |
$3,100 |
$3,900 |
$2,900 |
$4,000 |
$13,900 |
|
|
Formal Consultation |
Low |
$3,100 |
$3,900 |
$2,900 |
$4,000 |
$13,900 |
|
High |
$6,100 |
$6,500 |
$4,100 |
$5,600 |
$22,300 |
|
|
Notes: Low and high estimates primarily reflect variations in staff wages and time involvement by staff. Technical assistance calls also have educational benefits to the landowner or manager and to the Service. Third parties are defined as State agencies, local municipalities, and private parties. Biological Assessment costs apply to all formal consultations and all upper-bound (high) informal consultations. Costs may not sum due to rounding. Sources: IEc analysis based on data from the Federal Government General Schedule Rates, 2002, Office of Personnel Management, and level of effort information from Biologists in the U.S. Fish and Wildlife Service, Asheville, NC and Cookeville, TN Fish and Wildlife Offices. |
||||||
Exhibit 4-2 displays
revised estimates of the total consultation costs associated with activities
affecting the proposed critical habitat for the heelsplitter. The cost estimates
were calculated by multiplying the number of expected consultations or technical
assistance calls (shown in Exhibits 3-1 and 3-2 of the DEA) by the
per effort cost of these actions. Based on this analysis, the upper-bound
total cost of consultations attributable to section 7 activities affecting
the heelsplitter or its critical habitat is estimated to range from $1,119,000
to $4,261,000. The Federal government will incur the majority of the costs,
with the Service incurring costs of $381,000 to $1,124,000 and other Federal
agencies incurring costs of $426,000 to $2,005,000. Costs to the States of
North Carolina and South Carolina, local municipalities, and private landowners
are expected to range from $312,000 to $1,132,000.
|
Exhibit
4-2 ESTIMATED
TOTAL CONSULTATION COSTS ATTRIBUTABLE TO |
|||||
|
Action |
Range |
Costs to the Service |
Costs to Other Federal Agencies |
Costs to Third Parties |
Total Costs |
|
Technical Assistance |
Low |
$52,000 |
$0 |
$120,000 |
$172,000 |
|
High |
$136,000 |
$0 |
$300,000 |
$436,000 |
|
|
Informal Consultation |
Low |
$301,000 |
$391,000 |
$130,000 |
$822,000 |
|
High |
$933,000 |
$1,946,000 |
$745,000 |
$3,624,000 |
|
|
Formal Consultation |
Low |
$28,000 |
$35,000 |
$62,000 |
$125,000 |
|
High |
$55,000 |
$59,000 |
$87,000 |
$201,000 |
|
|
Total |
Low |
$381,000 |
$426,000 |
$312,000 |
$1,119,000 |
|
High |
$1,124,000 |
$2,005,000 |
$1,132,000 |
$4,261,000 |
|
|
Note: Third parties are defined as State agencies, local municipalities, and private parties. Costs may not sum due to rounding. Sources: IEc analysis based on data from the Federal Government General Schedule Rates, 2002, Office of Personnel Management, and information from biologists in the U.S. Fish and Wildlife Service, Asheville, NC office. |
|||||
|
Exhibit 4-3 ESTIMATED
SECTION 7 TECHNICAL ASSISTANCE AND CONSULTATION COSTS FOR THE |
|||||
|
Unit |
Total Eforts |
Informal Consultations Total Costs |
Total Efforts |
Formal Consultations Total Costs |
Total Costs |
|
Unit 1 |
70 |
$239,000-$958,000 |
6 |
$83,000-$134,000 |
$322,000-$1,092,000 |
|
Unit 2 |
43 |
$134,000-$541,000 |
3 |
$42,000-$67,000 |
$176,000-$608,000 |
|
Units 1 & 2 |
3 |
$7,000-$33,000 |
0 |
$0 |
$7,000-$33,000 |
|
Unit 3 |
3 |
$8,000-$36,000 |
0 |
$0 |
$8,000-$36,000 |
|
Unit 4 |
4 |
$12,000-$50,000 |
0 |
$0 |
$12,000-$50,000 |
|
Unit 5 |
103 |
$237,000-$1,133,000 |
0 |
$0 |
$237,000-$1,133,000 |
|
Unit 6 |
78 |
$185,000-$873,000 |
0 |
$0 |
$185,000-$873,000 |
| Subtotal |
$822,000-$3,624,000 |
9 |
$125,000-$201,000 |
$947,000-$3,825,000 |
|
|
Technical Assistance |
200 |
||||
|
$172,000-$436,000 |
|||||
|
Total Number and Costs of Technical Assistance and Consultations |
301 |
9 |
|
510 |
|
|
$822,000-$3,624,000 |
|
$125,000-$201,000 |
$1,119,000-$4,261,000 |
||
|
a This analysis assumes that all of the consultations will involve costs to the Service, an Action agency, and a third party. b Many of the technical assistance costs cannot be attributed to individual units. As such, total technical assistance costs have been reported separately. Note: Costs may not sum due to rounding. |
|||||
Section
4.3 Estimated
Number and Costs of Forecast Project Modifications
Several commentors suggested that the estimated per-effort project modification costs presented in the DEA are too high. The sections below provide updated information on project modification costs.
The DEA focuses on impacts to the local timber economy in the Sumter National Forest, and does not attempt to calculate whether the National Forest's timber sale program is profitable for these particular actions. Such an analysis for these particular forecast sales is beyond the scope of this analysis. The opportunity cost of lost timber sales due to the presence of a riparian buffer zone was derived using cost estimates from personnel at the Sumter National Forest, based on current base rates for timber sales. This analysis maintains the same cost estimates as the DEA, with the per-effort cost of conservation measures for the heelsplitter expected to range between $3,000 and $4,000.
4.3.2 Modifications Associated with Formal Consultations
NCDOT commented that the project modification costs reported in the DEA for formal consultations are consistently too high, and fail to take into account the cost savings that can stem from proactive conservation efforts initiated by Action agencies. For example, NCDOT is required to mitigate lost habitat under section 404 of the Clean Water Act. By preserving heelsplitter habitat, NCDOT can gain "preservation credits" that may be applied to other road and bridge construction projects, reducing mitigation costs for those projects. In addition, NCDOT emphasized their efforts to incorporate protective measures for endangered species early in the project planning stages. By incurring some minor additional costs early on, NCDOT can avoid adverse impacts to listed species and subsequently avoid entering the more costly formal consultation process.
This analysis acknowledges that the formal consultation project modification costs outlined in the DEA may be too high. Nevertheless, given that they are upper-bound costs, the analysis maintains the same project modification costs as the DEA, with the following exceptions:
4.3.3 Estimated Costs of Project Modifications
Exhibit 4-4 presents updated per-effort estimates of total project modification costs associated with section 7 activities affecting the heelsplitter and its critical habitat. Exhibits 4-5 and 4-6 present estimates of total project modification costs associated with section 7 activities affecting the heelsplitter. Exhibit 4-7 presents the project modifications for the heelsplitter by unit and type of modification.
|
Exhibit 4-4 ESTIMATED
ECONOMIC COSTS ASSOCIATED WITH POTENTIAL PROJECT MODIFICATIONS |
|||||
|
Potential Project Modification (per project) |
Activity |
Informal |
Formal |
||
|
Low |
High |
Low |
High |
||
|
Erosion and Stormwater Control |
Residential Development |
$100,000 |
$800,000 |
$100,000 |
$800,000 |
|
Road/Bridge Construction |
$5,000 |
$10,000 |
$5,000 |
$10,000 |
|
|
Design Changes |
Residential Development |
$5,000 |
$10,000 |
$5,000 |
$10,000 |
|
Conservation Measures |
Residential Development |
$0 |
$0 |
$50,000 |
$150,000 |
|
Road/Bridge Construction |
$0 |
$0 |
$50,000 |
$150,000 |
|
|
Forestry |
$3,000 |
$4,000 |
$0 |
$0 |
|
|
Water Quality Monitoring |
Residential Development |
$0 |
$0 |
$5,000 |
$30,000 |
|
Road/Bridge Construction |
$0 |
$0 |
$5,000 |
$30,000 |
|
|
Habitat Restoration and Enhancement |
Residential Development |
$0 |
$0 |
$0 |
$200,000 |
|
Road/Bridge Construction |
$0 |
$0 |
$0 |
$200,000 |
|
|
Total |
Residential Development |
$105,000 |
$810,000 |
$160,000 |
$1,190,000 |
|
Road/Bridge Construction |
$5,000 |
$10,000 |
$60,000 |
$390,000 |
|
|
Forestry |
$3,000 |
$4,000 |
$0 |
$0 |
|
|
Note:
Costs may not sum due to rounding.
Source: Based on IEc review of past consultation history and information from Service Biologists, Asheville, NC. |
|||||
|
Exhibit 4-5 ESTIMATED SECTION 7 PROJECT MODIFICATION COSTS ASSOCIATED WITH INFORMAL CONSULTATIONS INVOLVING THE HEELSPLITTER (TOTAL OVER TEN YEARS) |
||||
|
Types of Project Modifications |
Land Use Activity Affected |
Per-Effort Cost of Project Modification |
Number of Consultations Recommending Modification |
Total Costs of Project Modifications |
|
Erosion and Stormwater Control |
Residential Development |
$100,000-$800,000 |
64 |
$6,400,000-$51,200,000 |
|
Road/Bridge Construction |
$5,000-$10,000 |
23 |
$115,000-$230,000 |
|
|
Design Changes |
Residential Development |
$5,000-$10,000 |
64 |
$320,000-$640,000 |
|
Conservation Measures |
Residential Development |
$0 |
n/a |
$0 |
|
Road/Bridge Construction |
$0 |
n/a |
$0 |
|
|
Forestry |
$3,000-$4,000 |
85 |
$255,000-$340,000 |
|
|
Water Quality Monitoring |
Residential Development |
$0 |
n/a |
$0 |
|
Road/Bridge Construction |
$0 |
n/a |
$0 |
|
|
Habitat Restoration and Enhancement |
Residential Development |
$0 |
n/a |
$0 |
|
Road/Bridge Construction |
$0 |
n/a |
$0 |
|
|
Total Costs of Project Modifications $7,090,000-$52,410,000 |
||||
|
Note: Costs may not sum due to rounding. |
||||
|
Exhibit 4-6 ESTIMATED SECTION 7 PROJECT MODIFICATION COSTS ASSOCIATED WITH FORMAL CONSULTATIONS INVOLVING THE HEELSPLITTER (TOTAL OVER TEN YEARS) |
||||
|
Types of Project Modifications |
Land Use Activity Affected |
Per-Effort Cost of Project Modification |
Number of Consultations Recommending Modification |
Total Costs of Project Modifications |
|
Erosion and Stormwater Control |
Residential Development |
$100,000-$800,000 |
5 |
$500,000-$4,000,000 |
|
Road/Bridge Construction |
$5,000-$10,000 |
3 |
$15,000-$30,000 |
|
|
Design Changes |
Residential Development |
$5,000-$10,000 |
5 |
$25,000-$50,000 |
|
Conservation Measures |
Residential Development |
$50,000-$150,000 |
5 |
$250,000-$750,000 |
|
Road/Bridge Construction |
$50,000-$150,000 |
3 |
$150,000-$450,000 |
|
|
Water Quality Monitoring |
Residential Development |
$5,000-$30,000 |
5 |
$25,000-$150,000 |
|
Road/Bridge Construction |
$5,000-$30,000 |
3 |
$15,000-$90,000 |
|
|
Habitat Restoration and Enhancement |
Residential Development |
$0-$200,000 |
5 |
$0-$1,000,000 |
|
Road/Bridge Construction |
$0-$200,000 |
3 |
$0-$600,000 |
|
|
Total Costs of Project Modifications$980,000-$7,120,000 |
||||
|
Note: Costs may not sum due to rounding. |
||||
In order to arrive at an estimate
of total costs of future project modifications likely to be recommended as a
result of section 7 activities for the heelsplitter, this analysis assumes that
some percentage of the total consultations for each activity will result in
modifications. The total number of consultations likely to recommend project
modifications are calculated by multiplying the total number of consultations
for each activity (Exhibits 3-1 and 3-2) by the percentage of consultations
recommending the modifications for each activity as follows:
Similarly,
to calculate the number of consultations likely to recommend project modifications
by unit, the total number of consultations for each activity per unit is multiplied
by the percentage of consultations recommending the modifications for each activity
(i.e., informal residential and road/bridge construction activities 80%; Informal
forestry activites 50%).
|
Exhibit 4-7 ESTIMATED
SECTION 7 PROJECT MODIFICATION COSTS FOR THE HEELSPLITTER BY CRITICAL
HABITAT UNIT |
|||
|
Unit Affected |
Consultations Recommending Modification |
Type of Project Modifications |
Total Costs of Project Modifications |
|
Unit 1 |
57 |
Erosion Control |
$4,370,000-$34,540,000 |
|
43 |
Design Changes |
$215,000-$430,000 |
|
|
5 |
Conservation Measures |
$250,000-$750,000 |
|
|
5 |
Water Quality Monitoring |
$25,000-$150,000 |
|
|
5 |
Habitat Restoration |
$0-$1,000,000 |
|
|
Unit 2 |
31 |
Erosion Control |
$2,245,000-$17,690,000 |
|
22 |
Design Changes |
$110,000-$220,000 |
|
|
3 |
Conservation Measures |
$150,000-$450,000 |
|
|
3 |
Water Quality Monitoring |
$15,000-$90,000 |
|
|
3 |
Habitat Restoration |
$0-$600,000 |
|
|
Unit 3 |
1 |
Erosion Control |
$5,000-$10,000 |
|
Unit 4 |
2 |
Erosion Control |
$10,000-$20,000 |
|
Unit 5 |
50 |
Conservation Measures |
$150,000-$200,000 |
|
Unit 6 |
4 |
Erosion Control |
$400,000-$3,200,000 |
|
4 |
Design Changes |
$20,000-$40,000 |
|
|
35 |
Conservation Measures |
$105,000-$140,000 |
|
|
Total Costs of Project Modifications $8,070,000-$59,530,000 |
|||
|
Note: Costs may not sum due to rounding. |
|||
4.4 Total Section 7 Costs
The cost estimates presented in Exhibit 4-8 are a function of the assumed number of project modifications associated with activities affecting the heelsplitter and its critical habitat, along with the per effort costs outlined above. Based on this analysis, the total section 7 costs for the heelsplitter may range from $8,070,000 to $59,530,000 over the next ten years. As noted in the addenda and the DEA, these estimates are more likely to over-state than under-state costs.
|
Exhibit 4-8 UPPER-BOUND
ESTIMATE OF TOTAL PROJECT MODIFICATION COSTS ASSOCIATED WITH THE LISTING
AND DESIGNATION OF CRITICAL HABITAT FOR THE HEELSPLITTER |
|||||
|
Action |
Activity |
Number of Consultations Requiring Modifications |
Scenario |
Project Modification Costs |
Party Paying for Modifications |
|
Informal Consultation Project Modification |
Residential Development |
64 |
Low |
$6,720,000 |
Private developers (third party) |
|
High |
$51,840,000 |
||||
|
Road/Bridge Construction |
23 |
Low |
$115,000 |
DOT (action agency) |
|
|
High |
$230,000 |
||||
|
Forestry |
85 |
Low |
$255,000 |
U.S. Forest Service (action ageny) |
|
|
High |
$340,000 |
||||
|
Total |
172 |
Low |
$7,090,000 |
|
|
|
High |
$52,410,000 |
||||
|
Formal Consultation Project Modification |
Residential Development |
5 |
Low |
$800,000 |
Private developers (third party) |
|
High |
$5,950,000 |
||||
|
Road/Bridge Construction |
3 |
Low |
$180,000 |
DOT (action agency) |
|
|
High |
$1,170,000 |
||||
|
Total |
8 |
Low |
$980,000 |
|
|
|
High |
$7,120,000 |
||||
|
Total Project Modification Costs |
180 |
Low |
$8,070,000 |
|
|
|
High |
$59,530,000 |
||||
|
Note: Third parties are defined as State agencies, local municipalities, and private parties. * The number of consultations requiring modifications is based on the assumption that 80 percent of residential and road/bridge construction, and 50 percent of forestry informal consultations, and 100 percent of residential and road/bridge construction formal consultations with the ACOE, U.S DOT, and the U.S. Forest Service, will require modifications. Note: Costs may not sum due to rounding. Sources: IEc analysis based on data from the Federal Government General Schedule Rates, 2002, Office of Personnel Management, and information from biologists in the U.S. Fish and Wildlife Service, Asheville, NC Field Office. |
|||||
4.6 Economic
Impacts Associated Solely with the Designation of Critical Habitat
The cost estimates presented in Exhibit 4-9 are an indication of the total costs that may be associated with future potential section 7 consultations on the heelsplitter and its designated critical habitat over the next ten years. These represent costs likely to be incurred by the Service, Federal Action agencies, and non-Federal third parties for activities having a Federal nexus, which would require consultation under section 7 of the Act. However, the listing of the heelsplitter and the resultant Federal responsibility to avoid projects that would jeopardize the continued existence of the species is likely to trigger all of the impacts presented in the DEA. Therefore, the technical assistance efforts, section 7 consultations, and project modifications presented in Exhibits 4-9 and 4-10 are likely to occur over the next ten years even if critical habitat is not designated.
|
Exhibit 4-9 ESTIMATED
TOTAL CONSULTATION COSTS ATTRIBUTABLE TO POTENTIAL FUTURE SECTION 7 CONSULTATIONS
ON THE HEELSPLITTER AND
ITS CRITICAL HABITAT |
|||||
|
Action |
Range |
Costs to the Service |
Costs to Other Federal Agencies | Cost to Third Parties | Total Costs |
|
Technical Assistance |
Low |
$52,000 |
$0 |
$120,000 |
$172,000 |
|
High |
$136,000 |
$0 |
$300,000 |
$436,000 | |
|
Informal Consultation |
Low |
$301,000 |
$391,000 |
$130,000 |
$822,000 |
|
High |
$933,000 |
$1,194,000 |
$745,000 |
$3,624,000 |
|
|
Formal Consultation |
Low |
$28,000 |
$35,000 |
$62,000 |
$125,000 |
|
High |
$55,000 |
$59,000 |
$87,000 |
$201,000 |
|
|
Informal Consultation Project Modifications |
Low |
$0 |
$370,000 |
$6,720,000 |
$7,090,000 |
|
High |
$0 |
$570,000 |
$51,840,000 |
$52,410,000 |
|
|
Formal Consultation Project Modifications |
Low |
$0 |
$180,000 |
$800,000 |
$980,000 |
|
High |
$0 |
$1,170,000 |
$5,950,000 |
$7,120,000 |
|
|
Total Costs |
Low |
$381,000 |
$976,000 |
$7,832,000 |
$9,189,000 |
|
High |
$1,124,000 |
$3,745,000 |
$58,922,000 |
$63,791,000 |
|
|
Note: Third parties are defined as State agencies, local municipalities, and private parties. The large range between the lower- and upper-bound cost estimates is attributable to the uncertainty associated with the average size of residential developments and the per-effort project modifications that may be required. Costs may not sum due to rounding. Sources: IEc analysis based on data from the Federal Government General Schedule Rates, 2002, Office of Personnel Management, and information from biologists in the U.S. Fish and Wildlife Service, Asheville, NC office. |
|||||
|
Exhibit 4-10 TOTAL
SECTION 7 COSTS ASSOCIATED WITH THE LISTING AND DESIGNATION OF CRITICAL
HABITAT FOR THE HEELSPLITTER BY UNIT |
||||
|
Unit |
Informal Consultations |
Formal Consultations |
Informal Consultations with Project Modifications |
Total Section 7 Costs |
|
Unit 1 |
$239,000-$958,000 |
$83,000-$134,000 |
$4,860,000-$36,870,000 |
$5,182,000-$37,847,000 |
|
Unit 2 |
$134,000-$541,000 |
$42,000-$67,000 |
$2,520,000-$19,050,000 |
$2,696,000-$19,658,000 |
|
Units 1 & 2 |
$7,000-$33,000 |
$0 |
n/a |
$7,000-$33,000 |
|
Unit 3 |
$8,000-$36,000 |
$0 |
$5,000-$10,000 |
$13,000-$46,000 |
|
Unit 4 |
$12,000-$50,000 |
$0 |
$10,000-$20,000 |
$22,000-$70,000 |
|
Unit 5 |
$237,000-$1,133,00 |
$0 |
$150,000-$200,000 |
$387,000-$1,333,000 |
|
Unit 6 |
$185,000-$873,000 |
$0 |
$525,000-$3,380,000 |
$710,000-$4,253,000 |
|
Total |
$822,000-$3,624,000 |
$125,000-$201,000 |
$8,070,000-$59,530,000 |
$9,017,000-$63,355,000 |
|
Total Technical Assistance |
$172,000-$436,000 |
|||
|
TOTAL |
$822,000-$3,624,000 |
$125,000-$201,000 |
$8,070,000-$59,530,000 |
$9,189,000-$63,791,000 |
|
Note: Costs may not sum due to rounding. The large range between the lower- and upper-bound cost estimates is attributable to the uncertainty associated with the average size of residential developments and the per-effort project modifications that may be required. |
||||
POTENTIAL BENEFITS OF PROPOSED CRITICAL HABITAT
Several of the comments received on the DEA addressed the failure of the DEA to address the benefits associated with the designation of critical habitat for the heelsplitter. There is little disagreement in the published economics literature that real social welfare benefits can result from the conservation and recovery of endangered and threatened species (Bishop (1978, 1980), Brookshire and Eubanks (1983), Boyle and Bishop (1986), Hageman (1985), Samples et al. (1986), Stoll and Johnson (1984). Such benefits have also been ascribed to preservation of open space and biodiversity (see examples in Pearce and Moran (1994) and Fausold and Lilieholm (1999) both of which are associated with species conservation. Likewise, a regional economy can benefit from the preservation of healthy populations of endangered and threatened species, and the habitat on which these species depend.
It is not feasible, however, to fully describe and accurately quantify these benefits in the specific context of this economic analysis. For example, most of the studies in the economics literature do not allow for the separation of the benefits of listing (including the Act’s take provisions) from the benefits of critical habitat designation. The discussion presented in this report provides examples of potential benefits, which derive primarily from the listing of the species, based on information obtained in the course of developing the economic analysis. It is not intended to provide a complete analysis of the benefits that could result from section 7 of the Act in general or critical habitat designation in particular. In short, the Service believes that the benefits of critical habitat designation are best expressed in biological terms that can be weighed against the expected cost impacts of the rulemaking.
REFERENCES
Personal Communication with South Carolina Department of Transportation, April 19, 2002.
Statewide Transportation Improvement Program: South Carolina’s Five Year Transportation Program, October 1, 2000 - September 30, 2005.
Personal Communication with U.S. Army Corps of Engineers, Charleston District Office, South Carolina, January 11, 2002.
Personal Communication with U.S. Army Corps of Engineers, Asheville Regulatory Field Office, North Carolina, January 7, 2002.
Personal Communication with North Carolina Department of Transportation, Roadside Environmental Division, December 21, 2001 and April 24, 2002.
Comment Letter from John Kent to U.S. Fish and Wildlife Service, Asheville Office, April 5, 2002.
Comment Letter from Southern Appalachian Biodiversity Project to U.S. Fish and Wildlife Service, Asheville, Office, March 21, 2002.
Comment Letter from Southern Appalachian Biodiversity Project to U.S. Fish and Wildlife Service, Asheville Office, April 2, 2002.
Comment Letter from South Carolina Department of Transportation to U.S. Fish and Wildlife Service, Asheville Field Office, March 22, 2002.
Comment Letter from North Carolina Department of Transportation to U.S. Fish and Wildlife Service, Asheville Field Office, April 4, 2002.
Comment Letter from North Carolina Department of Administration to U.S. Fish and Wildlife Service, Asheville Field Office, April 3, 2002.
U.S. Fish
and Wildlife Service
Southeast Region
1875 Century Boulevard
Atlanta, GA 30345
404-679-7244
http://southeast.fws.gov