|
|
360 FW 4 |
FWM#: 456 (Supersedes 360 FW 4, 06/10/03, FWM 423 and Director’s Order 171, 05/21/04) Date: November 22, 2004 Series: Engineering and Construction Part 360: Engineering and Construction Management Originating Office: Division of Engineering |
|
|
|
4.1 What is the objective of this program? To manage and inspect construction projects to ensure Service facilities are built as designed.
4.2 What are the authorities for this program?
A. 485 DM 24 (Contractor Safety and Health).
H. Payments. The CO will make all payments and retainages according to FAR requirements.
K. Contract Modifications. Contract modifications allow the CO to change an ongoing construction contract for one of three possible reasons. For all three scenarios described below, the CO issues a Request for a Cost Proposal to the contractor, and the contractor must estimate the costs and time for the change. Before issuing the modification, the CO will need a detailed description of the desired change from the COR/CI along with a justifiable and detailed cost estimate, time schedule, and funding to support the change. The COR/CI will put together necessary documentation required by the CO so that the COR/CI can advise the CO on technical matters related to the proposed change. The COR/CI will not consult the contractor for pricing information nor negotiate the modification without the CO’s approval.
(1) The Government wants a change to correct an error or omission to the contract documents.
L. Final Inspection and Acceptance. Final inspection is an important aspect of contract administration, since warranty clauses may not exist in contracts for some construction and rehabilitation projects. If they do exist, their coverage may not be as comprehensive as the Government's rights under other clauses of the contract. Before completing a final inspection, the COR/CI will prepare and provide the contractor a “punch list” (refer to SCIH, Exhibit 7.2 for punch list example) of items requiring correction. Give the contractor adequate time to complete the punch list items before the final inspection. The purpose of the final inspection is to determine whether or not the work accomplished and materials/equipment furnished meet specifications. The COR will verify that the construction project is complete and the contract specifications are fulfilled in the final inspection and submit a statement of completion to the CO. The COR/CI will complete a final inspection before the contract expires. After final inspection and acceptance, the contractor will correct any remaining punch list items within the time limit approved by the CO.
(1) Service Construction Inspection Handbook (SCIH).
4.6 What are the requirements and procedures for Force Account construction?
(2) Significant electrical systems or environmental concerns.
(4) Critical life safety code factors.
PDM Web sites: Centralized Library of Servicewide Policies | FWS Forms | PDM Services
Privacy, Disclaimer and Copyright Information | Information Quality Act