Detroit River International Wildlife Refuge
Midwest Region
Best Management Practices for
Soft Engineering

of Shorelines
Based on a Binational Conference Sponsored by the
Greater Detroit American Heritage River Initiative and Partners

Chapter 12

Soil Bioengineering for Streambank Protection and Fish Habitat Enhancement, Collingwood, Ontario (Rick Grillmayer, Nottawasaga Valley Conservation Authority)

Introduction

The goal of this project was to repair and stabilize an eroding streambank with the use of vegetation, to create in-stream cover by constructing a vegetated structure, and to create a demonstration site that displays the effective use of soil bioengineering technology.

Project Description

The Black Ash Creek Project was initiated in 1992 as a component of the Collingwood Harbour Remedial Action Plan. The overall objectives of this watershed project were to reduce sediment loading from the creek into the harbor and enhance fish and wildlife habitat. Black Ash Creek was identified as contributing approximately 90% of the suspended sediment load for Collingwood Harbour (Collingwood Harbour RAP Stage 2 Document 1992). Sources of this sediment include erosion induced by cattle grazing on steep escarpment areas and eroding streambanks.

The location of this project is the Thompson Property on the 10th concession, Town of Collingwood. The reduction of channel sinuosity and elimination of a functioning floodplain had created an unstable reach of stream with significant erosion. The channel had been placed in a roadside ditch and the shoulder of the road was eroding. A previous attempt to stabilize this channel with field stone had failed because the improperly sized and placed stone was being eroded by high stream velocities. The stream gradient was steep (3.1%) and once the bed armor was missing the streambed degraded, aggravating the eroding bank. The bank slope on both sides was nearly vertical. The stream is intermittent, with flows occurring only during snowmelt and storm events. The catchment area upstream of the project site is approximately 10 km2.

Bank stabilization and streambed armoring took place during the fall of 1993. The confined nature of the channel prevented excavating a flood plain or sloping the banks to a stable angle. The east side of the channel was privately owned and the owner was not open to any loss of property that would occur if regrading was used. It was decided to construct a bioengineered cribwall. This structure would stabilize a vertical bank and require little room. The streambed was armored to prevent down cutting. No attempt was made at this time to stabilize the road shoulder directly opposite the project site, however, the Town of Collingwood did attempt to stabilize the road shoulder by constructing a concrete wall during the early summer of 1995. By the late fall of 1999, the concrete wall was beginning to show signs of failure. The soil bioengineered cribwall was holding well.

A soil bioengineered cribwall is a hollow, interlocking arrangement of timbers constructed as a wall. This structure is filled with suitable soil and a layer of live branch cuttings. Once the cuttings have taken root and grown, they will eventually take over the structural functions of the timbers. The end result is a stable, vegetated slope.

The cribwall was built into the bank so the face of the cribwall would be at the same location as the original face of the slope. This was done so the capacity of the channel would not be reduced. A hi-hoe was used to excavate the cribwall site. The logs for the cribwall were cut from a Nottawasaga Valley Conservation Authority jack pine plantation. The wall itself was built by hand and measured 30 m long, 1 m high, and 2.2 m wide at the bottom. The wall was canted back so that the top brush layers would not shade the bottom ones.

Shrub willow cuttings were harvested from sites within the watershed and transported to the cribwall site. Care was taken to time the harvest so that only fresh material would be used. Species of willow used at this site were:

  • Willow (Salix eriocephala);
  • Sandbar Willow (Salix exigua); and
  • Autumn Willow (Salix serrisima).

The cribwall was built by alternating layers of timbers, soil, and cuttings. Once the cribwall was completed, unused soil was removed from the site. Exposed soil was seeded with annual rye and oats. The soil was then covered with anti-wash geojute to prevent surface erosion. Live stakes (live rootable cuttings tamped into the ground) were placed at random into the geojute. The streambed was protected from down-cutting by placing 28 tons of rip-rap stone.

Due to the absence of any horizontal sinuosity, stream energy had to be dissipated by vertical sinuosity. This was achieved by placing the stone in a series of steps, attempting to establish a step-pool formation common to high gradient streams.

Regulatory Considerations

Whenever a project may impact the natural ecosystem, approvals and permits are needed. The project was approved by the local Ministry of Natural Resources (Midhurst District) and a work permit was issued under the Lakes and Rivers Improvement Act. A permit from the Nottawasaga Valley Conservation Authority was required under the Fill, Construction, and Alterations to Waterways Regulation.

The stream at this site is intermittent. The fish community is predominantly cyprinids and catostomids, and is nonexistent through summer, fall, and winter. Fish are present, likely as migrants, during the spring. The cribwall was built during the fall, while the channel was dry. Sedimentation during construction was minimal. The addition of bed material would not have affected any fish or macroinvertebrates. Materials used were native and harvested from within the same sub-watershed as the cribwall.

Cost

Project costs are presented in Table 8. Costs do not include; tools, truck rental, fuel, office costs, indirect support for the crew, or permit fees. It would be impossible to separate these costs as they were used/required on more than one site.


Table 8. Soil bioengineering costs associated with soft engineering of Black Ash Creek.

Requirements
Cost
 
Requirements
Time(hrs)
Cost
Consultants
$800
Measuring and Design
48
$772
Logs for Cribwall
$50
Site Preparation
27
$311
Contractors
$1,423
Cutting/transporting Materials
48
$553
Rock
$300
Placement of Materials
148
$1,244
Geojute
$297
Repairs to Lawns
72
$138
Spikes
$122
     
Refreshments
$56
Total Wages
343
$3,018
Fertilizer/seed
$40
Note: Costs listed were specific to this site only.
Topsoil
$250
Rental of Lawn Rollers
$10
   
Total Materials
$3,348


Funding and Implementation Partners

Environment Canada Great Lakes 2000 Cleanup Fund;
Environment Canada Environmental Partners Fund;
Ontario Ministry of Natural Resources;
Ontario Ministry of Environment;
Nottawasaga Valley Conservation Authority;
Collingwood Collegiate Institute;
Collingwood Rotary Club; and
Landowners in the Black Ash Creek Watershed.

Post Project Evaluation of Effectiveness

1995: Two years after completion, the streambank at this site was completely vegetated (Figure 39). Any erosion was insignificant. The soil bioengineered cribwall successfully weathered the spring flows, which often saw the structure completely submerged. Growth from the cuttings has been vigorous, with Salix eriocephala becoming the dominant willow.

2000: Seven years after completion, the streambank at this site is still doing very well. The concrete block wall built by the Town of Collingwood is beginning to show signs of failure (Figure 40). This failure is apparent in the form of undercutting, the slumping of several sections of wall, and widespread cracking and deterioration of the concrete. The soil bioengineered cribwall is more than adequately maintaining stability (Figure 41).

Figure 39. Conditions of Black Ash Creek project site on June 28, 2000. Soil bioengineered cribwall is on the left side of the photograph, the concrete block wall is on the right.

Black Ash Creek site

Figure 40. Deterioration of the concrete block wall, showing undermining and slumping of the structure on June 28, 2000.

wall deterioration

Figure 41. Close-up of soil bioengineering cribwall on June 28, 2000.

cribwall close up


Conclusion

This project was an overwhelming success.

Benefits of the Project

Soil bioengineering was chosen as the preferred method of streambank stabilization for several reasons:

  • It is an applied science that combines structural, biological, and ecological concepts to construct living structures for erosion, sediment, and flood control. Conventional methods of erosion and flood control provide little habitat for terrestrial or aquatic organisms. Conventional structures often have the effect of an ecological barrier, separating aquatic and terrestrial; conversely, the vegetation used in bioengineered structures provide a wide range of habitats for many organisms.
  • Soil bioengineered structures are labor intensive, not capital or energy intensive (limited budget dollars were put into wages, not materials).
  • This is a living wall (there is usually less long-term maintenance than conventional structures since soil bioengineered structures tend to be self-repairing).
  • The project serves as an excellent demonstration of the strength and applicability of soil bioengineering as a method of managing erosion in high-energy stream channels. The site can be readily seen by the public and the presence of a conventional concrete block wall directly opposite of the soil bioengineered wall provides a direct comparison of the two methods.

 

References

Collingwood Harbour RAP Team. 1992. Collingwood Harbour Remedial Action Plan Stage 2 Report: a Strategy for Restoring the Collingwood Harbour Ecosystem and Delisting Collingwood Harbour as an Area of Concern (In consultation with the Public Advisory Committee).

Dobbs, F., and Grillmayer, R. 1994. Black Ash Creek Rehabilitation Project Implementation Report. Collingwood Harbour Remedial Action Plan. ISBN 0-7778-2696-8. Ontario Ministry of the Environment, Toronto, Ontario, Canada.

Sotir, R., and D.H. Gray. 1989. Fill Slope Repair Using Soil Bioengineering Systems. IN: Public Works, December 1989.

 

Contact Person

Rick Grillmayer
Nottawasaga Valley Conservation Authority
266 Mill St.
Hwy 90, R.R.#1
Angus, Ontario L0M 1B0
nvca@bconnex.net, rgrillmayer@yahoo.ca

 

Report Home
chapter 13
Table of Contents
summary and overview
Greater Detroit American Heritage River Home
Last updated: July 9, 2008