What is a C.C.P.?
Please contact us with any questions or for more information.Cheri Ehrhardt321.861.2368 (phone) 321.861.1276 (fax) merrittislandCCP@fws.gov http://merrittisland.fws.gov/
Merritt Island NWR |
Merritt Island National Wildlife Refuge
The estimated timeline for this planning process is expected to span about 4 years. This timeline has the potential to be extended for a variety of reasons (e.g., additional time might be necessary to gather public input, to prepare the CCP and NEPA documents, and/or to conduct internal review of the documents). |
| Planning Phases |
Estimated Dates (dates are subject to change) |
| Conduct Preplanning | Summer 2001 - September 2002 |
| Initiate Public Scoping (Open House) | September 21, 2002 |
| Conduct Public Scoping | September 2002 - November 2002 |
| Conduct Intergovernmental Scoping | September 2002 - August 2003 |
| Prepare Draft CCP | August 2003 - February 2006 |
| Conduct Internal Review and Publish Draft CCP & EA | February 2006 - December 2006 |
|
Request Public Review & Comment |
December 27, 2006 - February 26, 2007 |
| Develop Final CCP | ~June 2007 |
| Sign Finding of No Significant Impact | ~July 2007 |
| Begin Implementation the CCP | ~September 2007 |